CIVIL WORKS :

 
     
 

All the work taken up during 2001-02 to  2004-05 have been  completed.  The works  taken during 2005-06 are in advanced stage of completion.   The cumulative progress of civil works is as given below:

 
 

 

 
 

Civil Works  Progress as on 31.08.2006

 
     
 

Sl. No

Name of the Work

Physical Progress.

Approved

Completed

progress

percentage of Completion

1

B.R.C.

70

66

4

94.29

2

C.R.C

1043

829

214

75.48

3

School Building

1556

1163

393

74.74

4

Addl. Class Room

14819

11962

2857

80.72

5

Toilets

23314

23046

268

98.85

6

Drinking water

21441

21172

269

98.75

7

Electricity

13585

13451

134

99.01

8

Compound Wall

3713

3700

13

99.65

 

Total

78541

75389

4152

94.78

 
     
  SDMCs construct school buildings, toilet, water supply and compound wall. Community is involved the construction. Construction of BRCs has been given to Zilla Panchayath Engineering Division, Karnataka Land Army Corporation (KLAC), NIrmithi Kendra, PWD.   
     
  Appointment of Consulting Engineer has been finalised.  One consultancy engineer per block and one at district level are provided.  Two consulting engineers and architects are provided at State level. The consultants appointed for 3rd party inspection have already started the inspection and review/action are being taken based on the reports received from the field by the engineers.  
     
  DISTRICT WISE DETAILS OF CIVIL WORKS FOR THE YEAR 2001-02 , 2002-03 2003-04 2004-05, 2005-06,  2006-07 (as on 31.08.2006)  
     
  Planning :  
     
  Planning process is decentralized. State level Core group for the Planning purpose is constituted. State level workshops were conducted to discuss various issues related to planning and to guide the district level core group in preparation plans and consultation procedures required to be followed.  The block level officials are trained at the district level. Draft plans are prepared at habitation level after extensive discussion in open meeting with community members and SDMC members and other village functionaries. The consolidation takes place at  cluster, block and at districts. The plans are discussed at the District Implementation Committee (DIC) and finalised.   In-house software to generate the costing sheets is developed.  The plans are further scrutinized at the SPO level and sent to MHRD after necessary updations/modifications  

horizontal rule

Home | Objective | Intevention | Finances | CivilWorks | Proceedings | AnnualReport | ContactUs

Any Queries regarding this web site should be directed to Nodal Officer, e-Gov Unit by email:  [miscpi.edu.karbng@mail.kar.nic.in]

Best Viewable in the browser Ver. 5 or higher at Screen area 1024 by 768 pixels.
Information provided on this Website is copyright of the respective copyright holders.
All registered trademarks are acknowledged.

Last updated: 07-Aug-2009.